Sr. No Activity Time Schedulesort descending
1 Valuation Certificate 03 Days
2 Tap Usage Conversion 03 Days
3 Incorporation Certificate 03 Days
4 Vacant Land Tax 03 Days
5 No House Certificate 03 Days
6 Boundary Certificate 05 Days
7 Tap Repairs 05 Days
8 Sound Certificate 07 Days
9 Sanitary Certificate 07 Days
10 D and O Trade License 07 Days
11 Advertisement Tax 07 Days
12 Tap Disconnection 07 Days
13 Demand Generation 07 Days
14 Death Certificate Application 07 Days
15 Birth Certificate Application 07 Days
16 Demand Extract 07 Days
17 New Tap Application-OYT 07 Days
18 Contractor Registration 15 Days
19 Tap Meter Connection 15 Days
20 New Tap Application Ordinary 15 Days